D02 · L3 · 01 — Capacity & Long-Range PlanningPlaneación de Capacidad y Largo Plazo

Rough-Cut Capacity Planning (RCCP)Planeación de Capacidad Rough-Cut (RCCP)

RCCP is the gate that turns a Master Production Schedule from a forecast into a commitment. Skip it and the bottleneck reality you ignored arrives in week three of the quarter — as missed deliveries that cost more to recover than the check would have cost to run.

RCCP es la compuerta que convierte un Master Production Schedule de un pronóstico en un compromiso. Sáltala y la realidad del cuello de botella que ignoraste llega en la semana tres del trimestre — como entregas incumplidas que cuestan más recuperar de lo que el filtro habría costado correr.

01What it isQué es

RCCP is the feasibility check that sits between the demand consensus and the detailed MRP run — a validation of whether the Master Production Schedule (MPS) is producible against the capacity of a handful of critical resources: bottleneck work centers, key shared cells, long-lead-time materials, and constrained skilled labor pools.

RCCP es el filtro de viabilidad entre el consenso de demanda y la corrida detallada de MRP — una validación de si el Master Production Schedule (MPS) es producible contra la capacidad de un puñado de recursos críticos: centros de trabajo cuello de botella, celdas compartidas clave, materiales de lead time largo y bolsas de mano de obra calificada restringidas.

02Why it mattersPor qué importa

It is the gate where the plan becomes credible — or doesn't. The MPS that passes RCCP is a commitment the plant can keep; the one that skips it is a forecast disguised as a plan. The dominant failure pattern is well-documented in capacity-constrained operations (Vollmann, Berry, Whybark & Jacobs, 2005 — textbook of record): schedules built on demand-side optimism collide with bottleneck reality in week three of the quarter, surfacing as missed deliveries that cost more to recover than they would have cost to prevent. The asymmetry is structural — capacity is committed in months but exposed in weeks, so an early signal is more valuable than a precise one.

Es la puerta donde el plan se vuelve creíble — o no. El MPS que pasa RCCP es un compromiso que la planta puede sostener; el que se la salta es un pronóstico disfrazado de plan. El modo de falla dominante está bien documentado en operaciones con capacidad restringida (Vollmann, Berry, Whybark y Jacobs, 2005 — texto de referencia): programas construidos sobre optimismo de demanda chocan con la realidad del cuello de botella en la tercera semana del trimestre, apareciendo como entregas faltantes que cuestan más recuperar que prevenir. La asimetría es estructural — la capacidad se compromete en meses pero se expone en semanas, así que una señal temprana vale más que una precisa.

03How it is doneCómo se hace

1
Build the Bill of Resources (BoR) before anything else. Map each product family to the critical resources it consumes — minutes per unit on each bottleneck, energy, operator-hours, changeover penalty per transition. Without it, the model is a guess.
2
Select 8–15 critical resources — no more. Use Theory of Constraints to identify bottlenecks, shared cells, long-LT imports and scarce skills. A bigger model is not a better one; it is a slower, noisier approximation of CRP.
3
Compute load by family, not SKU. RCCP is directional, not detailed. Aggregate to the level that captures meaningful constraint signal without forcing the planner into SKU-level noise.
4
Emit one of three signals: feasible, constrained, infeasible. A constrained signal demands quantified mitigation options (overtime, weekend shifts, co-manufacturing, alt routing). An infeasible signal sends the plan back to the demand review.
5
Convert every flagged constraint into pre-S&OP options with cost, time and risk attached. The executive S&OP does not discover constraints — it decides among options the pre-S&OP has already shaped.
6
Track predictive accuracy and re-calibrate the BoR semi-annually. Every RCCP signal is a forecast. Compare it to actual execution; feed misses back into BoR coefficients. Without this loop, the model decays silently into background noise.
Worked example — illustrative A semiconductor assembly & test operation runs its Q4 RCCP against 11 critical resources. The demand plan reflects a 38% volume lift from strong design wins. The model flags two infeasible constraints: a mix-cell wire-bond loaded at 142% for six weeks, and a substrate supplier at 156% with no capacity reservation. The pre-S&OP team converts each into options — accelerate qualification of a second cell ($1.8M capex, 14 weeks, +35% capacity), negotiate a substrate reservation contract at +8% unit cost, or defer two lower-margin SKUs into Q1. The executive S&OP chooses the substrate contract and the SKU deferral — $14.6M of margin protected on commitments that would otherwise have failed in week four.
1
Construye el Bill of Resources (BoR) antes que cualquier otra cosa. Mapea cada familia de producto a los recursos críticos que consume — minutos por unidad en cada cuello de botella, energía, horas-operador, penalización de cambio por transición. Sin él, el modelo es una conjetura.
2
Selecciona entre 8 y 15 recursos críticos — no más. Usa Teoría de Restricciones para identificar cuellos de botella, celdas compartidas, importaciones de LT largo y habilidades escasas. Un modelo más grande no es mejor; es una aproximación más lenta y ruidosa del CRP.
3
Calcula la carga por familia, no por SKU. RCCP es direccional, no detallado. Agrega al nivel que capture señal de restricción significativa sin forzar al planeador al ruido de nivel SKU.
4
Emite una de tres señales: viable, restringido, inviable. Una señal de restringido exige opciones de mitigación cuantificadas (tiempo extra, fines de semana, co-fabricación, ruteo alterno). Una señal de inviable regresa el plan a la revisión de demanda.
5
Convierte cada restricción señalizada en opciones para el pre-S&OP con costo, tiempo y riesgo. El S&OP ejecutivo no descubre restricciones — decide entre opciones que el pre-S&OP ya moldeó.
6
Rastrea la precisión predictiva y recalibra el BoR semestralmente. Cada señal RCCP es un pronóstico. Compárala contra la ejecución real; retroalimenta los errores a los coeficientes del BoR. Sin este ciclo, el modelo decae silenciosamente hasta convertirse en ruido de fondo.
Ejemplo trabajado — ilustrativo Una operación de ensamble y prueba de semiconductores corre su RCCP de Q4 contra 11 recursos críticos. El plan de demanda refleja un incremento de volumen del 38% por design wins fuertes. El modelo marca dos restricciones inviables: una celda de wire bond cargada al 142% durante seis semanas y un proveedor de sustrato al 156% sin reserva de capacidad. El equipo pre-S&OP convierte cada una en opciones — acelerar calificación de una segunda celda ($1.8M de capex, 14 semanas, +35% de capacidad), negociar contrato de reserva de sustrato a +8% de costo unitario, o diferir dos SKUs de menor margen a Q1. El S&OP ejecutivo elige el contrato de sustrato y el diferimiento de SKUs — $14.6M de margen protegido sobre compromisos que de otra forma habrían fallado en la semana cuatro.

04The concept in depthEl concepto a fondo

📋The Bill of Resources and the critical-resource set›
RCCP tests the MPS against a deliberately small set of critical resources — bottleneck work centers, key shared cells, long-lead materials, constrained skilled-labor pools — using a Bill of Resources that maps each end item to the critical capacity it consumes. The discipline is in keeping the set tight: a rough-cut check against everything is neither rough nor fast, and loses the early-warning speed that is its entire reason to exist.
⚖️Rough-cut vs detailed capacity planning›
RCCP is deliberately approximate and fast, run at the MPS level before the detailed MRP explosion; CRP (capacity requirements planning) is the finite, detailed check that comes after. The value of RCCP is timing — it flags infeasibility while the plan can still change cheaply, rather than discovering it in the detailed schedule when commitments are already made.
⏳The months-committed, weeks-exposed asymmetry›
Capacity is committed over months — hiring, qualification, tooling — but its insufficiency is exposed in weeks, when the schedule hits the constraint. This asymmetry is why an early, approximate RCCP signal beats a late, precise one: by the time the detailed plan proves infeasible, the window to add capacity has already closed and only expensive recovery remains.
📋El Bill of Resources y el conjunto de recursos críticos›
RCCP prueba el MPS contra un conjunto deliberadamente pequeño de recursos críticos — centros de trabajo cuello de botella, celdas compartidas clave, materiales de lead time largo, bolsas de mano de obra calificada restringida — usando un Bill of Resources que mapea cada ítem terminado a la capacidad crítica que consume. La disciplina está en mantener el conjunto apretado: un filtro rough-cut contra todo no es ni rough ni rápido, y pierde la velocidad de alerta temprana que es toda su razón de existir.
⚖️Capacidad rough-cut vs detallada›
RCCP es deliberadamente aproximado y rápido, corrido a nivel MPS antes de la explosión detallada de MRP; el CRP (capacity requirements planning) es el filtro finito y detallado que viene después. El valor de RCCP es el timing — marca la inviabilidad mientras el plan todavía puede cambiar barato, en vez de descubrirla en el programa detallado cuando los compromisos ya están hechos.
⏳La asimetría meses-comprometidos, semanas-expuestos›
La capacidad se compromete en meses — contratación, calificación, herramental — pero su insuficiencia se expone en semanas, cuando el programa pega contra la restricción. Esta asimetría es por qué una señal RCCP temprana y aproximada le gana a una tardía y precisa: para cuando el plan detallado prueba ser inviable, la ventana de agregar capacidad ya se cerró y solo queda la recuperación cara.

05In practiceEn la práctica

🎯Keep the critical-resource set tight›
Restrict RCCP to the handful of resources that actually constrain the plan, and review the set as bottlenecks shift. A bloated resource list slows the check and dilutes attention; the power of rough-cut is that it looks only where infeasibility actually originates.
🧮Generate quantified options per flagged constraint›
When RCCP flags an overload, hand the supply review a set of quantified options — overtime, alternate routing, pull-ahead, deferral — with cost and feasibility, not just a red flag. A constraint surfaced without options is an alarm; a constraint surfaced with options is a decision.
📊Measure the model's predictive accuracy›
Check quarterly whether the loads RCCP predicted matched what the critical resources actually experienced. A Bill of Resources drifts as routings and rates change; an RCCP model that is never validated against reality slowly becomes a confident, wrong feasibility check.
🔗Position RCCP inside the S&OP supply review›
RCCP is the analytical engine of the supply-balancing step: it is where the demand plan meets finite critical capacity. Wiring it into the S&OP supply review makes the feasibility check a governed gate rather than an optional analysis a planner runs when there is time.
🎯Mantén apretado el conjunto de recursos críticos›
Restringe RCCP al puñado de recursos que de verdad restringen el plan, y revisa el conjunto conforme cambian los cuellos de botella. Una lista inflada de recursos hace lento el filtro y diluye la atención; el poder del rough-cut es que mira solo donde la inviabilidad de verdad se origina.
🧮Genera opciones cuantificadas por restricción marcada›
Cuando RCCP marca una sobrecarga, entrega al supply review un set de opciones cuantificadas — tiempo extra, ruteo alterno, adelanto, diferimiento — con costo y viabilidad, no solo una bandera roja. Una restricción expuesta sin opciones es una alarma; una restricción expuesta con opciones es una decisión.
📊Mide la precisión predictiva del modelo›
Verifica trimestralmente si las cargas que RCCP predijo coincidieron con lo que los recursos críticos de verdad experimentaron. Un Bill of Resources deriva conforme cambian ruteos y tasas; un modelo RCCP que nunca se valida contra la realidad lentamente se vuelve un filtro de viabilidad seguro y equivocado.
🔗Posiciona RCCP dentro del supply review del S&OP›
RCCP es el motor analítico del paso de balanceo de oferta: es donde el plan de demanda se encuentra con la capacidad crítica finita. Conectarlo al supply review del S&OP hace del filtro de viabilidad una compuerta gobernada en vez de un análisis opcional que un planeador corre cuando hay tiempo.

06What you would useQué se usa

📌 RCCP / CAPACITY VALIDATION
🟦SAP IBP / S4 (RCCP) / o9 / Kinaxis — enterprise tier-1›
Native rough-cut and detailed capacity checks integrated with the MPS and the S&OP supply review, with Bill of Resources modeling. (SAP, o9, Kinaxis — vendor) The choice when the feasibility gate must sit inside the integrated plan.
🟩Blue Yonder / Oracle — capacity planning›
Solid RCCP/CRP modules with resource-load visualization and option modeling. (Blue Yonder, Oracle — vendor) A strong fit where the MPS-to-capacity check is the priority within an existing APS/ERP footprint.
🟥Finite-capacity / load-leveling specialists›
Dedicated capacity-modeling and load-leveling tools for complex resource networks. (specialized vendors — vendor) The vertical option when the critical-resource topology is intricate enough to exceed packaged RCCP.
⬜For operations that don't need a platform›
A Bill of Resources for the handful of critical resources and a load-vs-capacity check in a workbook, run at the MPS level each S&OP cycle. The discipline of testing the schedule against critical capacity before committing — not the tool — is what converts the MPS from a wish into a plan.
📌 RCCP / VALIDACIÓN DE CAPACIDAD
🟦SAP IBP / S4 (RCCP) / o9 / Kinaxis — enterprise tier-1›
Filtros de capacidad rough-cut y detallada nativos integrados con el MPS y el supply review del S&OP, con modelado de Bill of Resources. (SAP, o9, Kinaxis — vendor) La opción cuando la compuerta de viabilidad debe sentarse dentro del plan integrado.
🟩Blue Yonder / Oracle — planeación de capacidad›
Módulos sólidos de RCCP/CRP con visualización de carga de recursos y modelado de opciones. (Blue Yonder, Oracle — vendor) Un buen ajuste donde el filtro MPS-a-capacidad es la prioridad dentro de una huella APS/ERP existente.
🟥Especialistas en capacidad finita / nivelación de carga›
Herramientas dedicadas de modelado de capacidad y nivelación de carga para redes de recursos complejas. (vendors especializados — vendor) La opción vertical cuando la topología de recursos críticos es lo bastante intrincada para exceder el RCCP empaquetado.
⬜Para operaciones que no necesitan plataforma›
Un Bill of Resources para el puñado de recursos críticos y un filtro carga-vs-capacidad en un workbook, corrido a nivel MPS cada ciclo de S&OP. La disciplina de probar el programa contra la capacidad crítica antes de comprometer — no la herramienta — es lo que convierte el MPS de un deseo en un plan.
The bottom lineEn corto

The MPS that has not passed RCCP is not a plan — it is a wish. Own the Bill of Resources, keep the critical-resource set tight, generate quantified options for every flagged constraint, and measure the model's predictive accuracy quarterly. Capacity is committed in months but exposed in weeks; RCCP is the only mechanism that closes that asymmetry before customers do.

El MPS que no ha pasado por RCCP no es un plan — es un deseo. Apropia el Bill of Resources, mantén el conjunto de recursos críticos acotado, genera opciones cuantificadas para cada restricción señalizada y mide la precisión predictiva del modelo trimestralmente. La capacidad se compromete en meses pero se expone en semanas; RCCP es el único mecanismo que cierra esa asimetría antes de que lo hagan los clientes.