01What it isQué es
Stage-gate demand planning attaches a demand forecast, with an explicit uncertainty range, to every gate of the new-product process, so the range narrows from concept to launch and supply commitments grow only as confidence does.
El demand planning por Stage-Gate asocia un pronóstico de demanda, con un rango de incertidumbre explícito, a cada gate del proceso de nuevos productos, de modo que el rango se estrecha del concepto al lanzamiento y los compromisos de suministro crecen solo al ritmo de la confianza.
02Why it mattersPor qué importa
Most launch failures in the supply chain are timing failures: the forecast reaches production after packaging, materials and capacity are already locked. Stage-gate systems structure product development as stages separated by go/kill decision gates with defined deliverables (Cooper, 1990 — Business Horizons); making a demand forecast one of those deliverables brings supply chain in when its decisions still matter.
La mayoría de las fallas de lanzamiento en la cadena de suministro son fallas de tiempo: el pronóstico llega a producción cuando el empaque, los materiales y la capacidad ya están comprometidos. Los sistemas Stage-Gate estructuran el desarrollo de productos en etapas separadas por gates de decisión (avanzar o cancelar) con entregables definidos (Cooper, 1990 — Business Horizons); hacer del pronóstico de demanda uno de esos entregables integra a supply chain cuando sus decisiones todavía importan.
03How it is doneCómo se hace
04The concept in depthEl concepto a fondo
Advanced: designs the Stage-Gate demand planning process with the correct methods and accuracy for each gate; leads reconciliation with the supply plan; manages the NPI forecast transition to the statistical model when sufficient history exists.
Avanzado: diseña el proceso de demand planning por Stage-Gate con los métodos y la precisión correctos para cada gate; lidera la conciliación con el plan de suministro; gestiona la transición del pronóstico de NPI al modelo estadístico cuando ya existe historia suficiente.
05In practiceEn la práctica
06Illustrative caseCaso ilustrativo
A food company launches a new category (alternative proteins). The forecast evolves at each gate.
| Stage-Gate | Forecast method | Year 1 demand forecast |
|---|---|---|
| Gate 1 — Concept (12 months before launch) | Total market size × target share · Range: ±50% | 100,000–300,000 units/year · Company proceeds with development |
| Gate 2 — Development (6 months before) | Analogy with 3 similar new category launches · Sales team input · Range: ±30% | 160,000–280,000 units/year · Initial production plan calibrated with the range |
| Gate 3 — Pre-launch (8 weeks before) | Market test in Monterrey (4 weeks) · Defined distribution plan (180 points) · Range: ±20% | 195,000–255,000 units/year · Initial production: 220,000 units |
Una empresa de alimentos lanza una nueva categoría (proteínas alternativas). El pronóstico evoluciona en cada gate.
| Stage-Gate | Método de pronóstico | Pronóstico de demanda del año 1 |
|---|---|---|
| Gate 1 — Concepto (12 meses antes del lanzamiento) | Tamaño total del mercado × participación objetivo · Rango: ±50% | 100,000–300,000 unidades/año · La empresa avanza al desarrollo |
| Gate 2 — Desarrollo (6 meses antes) | Analogía con 3 lanzamientos similares de nuevas categorías · Insumos del equipo de ventas · Rango: ±30% | 160,000–280,000 unidades/año · Plan inicial de producción calibrado con el rango |
| Gate 3 — Prelanzamiento (8 semanas antes) | Mercado de prueba en Monterrey (4 semanas) · Plan de distribución definido (180 puntos) · Rango: ±20% | 195,000–255,000 unidades/año · Producción inicial: 220,000 unidades |
07How it is measuredCómo se mide
08What you would useQué se usa
Planning platforms with NPI demand planning modules managing the forecast by Stage-Gate gate.
SAP IBP manages the complete NPI lifecycle: from concept forecast to the statistical model transition after launch.
Plataformas de planeación con módulos de demand planning de NPI que gestionan el pronóstico por gate del Stage-Gate.
SAP IBP gestiona el ciclo de vida completo del NPI: desde el pronóstico de concepto hasta la transición al modelo estadístico después del lanzamiento.
If demand planning first sees a new product eight weeks before launch, the supply chain has already lost the launch.
Si demand planning ve un nuevo producto por primera vez ocho semanas antes del lanzamiento, la cadena de suministro ya perdió el lanzamiento.